NEW QUESTION 11
Your production planners must execute planning only for specific resources. How can you achive this in advanced Planning(PP/DS)
- A. Use a propagation range.
- B. Use a resource group.
- C. Use a planning group.
- D. Use heuristic.
Answer: D
NEW QUESTION 12
What are the possible results of a production planning run in Advanced Planning (PP/DS)?
- A. Stock transport order
- B. Purchase requistion
- C. Planned order
- D. Scheduling agreement schedule line
- E. Production order
Answer: B,C,D
NEW QUESTION 13
In the Capacity Scheduling Table, which settings can you select for the planning strategy? Note: There are 3 correct answers to this question.
- A. Fixed pegging
- B. Direction
- C. Finiteness level
- D. Planning mode
- E. Scheduling control
Answer: B,D,E
NEW QUESTION 14
Which item statuses can you select inside a material BOM?
- A. Service
- B. Sales
- C. Quality management
- D. Engineering
Answer: B,D
NEW QUESTION 15
Which of the following are possible configuration steps when setting up the alert monitor in Advance Planning?
- A. Assign the alert profile to the overall profile.
- B. Assign the overall profile to the authorization profile.
- C. Create object selection variant for product-related alerts.
- D. Create object selection variant for transportation lane-related alerts.
Answer: A,C
NEW QUESTION 16
What is the purpose of a reporting point confirmation in repetitive manufacturing?
- A. To provide timely updates of inventory management for the staged components
- B. To reduce the total production lead time for along production line
- C. To determine the work in progress along the production line
- D. To stage different components for a production line simultaneously
Answer: A,C
NEW QUESTION 17
What detremines whatherthe planned independent requirements in MRP are consumed by other requrements?
- A. Requirements profile
- B. Order type
- C. Consumption sequence procedure
- D. Requirements type
Answer: D
NEW QUESTION 18
You want to use capacity availability checks for production orders. Which settings have to be made for this?
- A. A checking rule must be assigned in the checking control
- B. An overall profile must be assigned in the checking control.
- C. The PRT Availability Check must be set in the checking control.
- D. The Relevant for Finite Scheduling indicator must be set
Answer: B,D
NEW QUESTION 19
Advanced Planning uses master data and transaction data from SAP S/4HANA. In which data objects can you set the advanced planning flag?
- A. Material
- B. Work center
- C. Production version
- D. Plant
Answer: A,B
NEW QUESTION 20
What does forecasting in demand planning cycle include?
- A. Past quotation quantities
- B. One-off events
- C. Market intelligence
- D. Past procurment quantities
- E. Past sales order quantites
Answer: B,C,E
NEW QUESTION 21
For a production version to be valid and consistent what requirements must be fulfilled?
- A. The deletion flag must NOT be set for the bill of materials (BOM) or the routing.
- B. The assigned routing must NOT have alternative sequences.
- C. The assigned routing and bill of materials (BOM) must be valid in the entire validity period.
- D. The lot size range must be within the lot-size range of the assigned routing.
- E. The assigned routing must be a rate routing.
Answer: A,C,D
NEW QUESTION 22
How can you limit the validity of a bill of material (BOM)?
- A. By period
- B. By plant
- C. By material type
- D. By industry
Answer: A,B
NEW QUESTION 23
What type of time element can be reduced by strategy settings while dispatching?
- A. Setup time
- B. Queue time
- C. Transportation time
- D. Wait time
Answer: B,D
NEW QUESTION 24
You want to set up a make-to-order planing scenario for finished material. The bil of material contains two components: one should be procured for each sales order individually, the other one shold be procured jointly for all independent requirements. Forcasting for the finished product is NOT possible. Which setting do you make to achive this?
- A. Choose planning strategy 50 (Planning whthout final assembly) and select corresponding Mixed MRP indicator
- B. Choose planning strategy 20 (Make-to-order) and select corresponding Invidual/collective indicator
- C. Choose planning strategy 50 (Planning whthout final assembly) and select corresponding Invidual/collective indicator
- D. Choose planning strategy 20 (Make-to-order) and select corresponding Mixed MRP indicator
Answer: C
NEW QUESTION 25
Which actions does the system preform by default when you save a confirmation for a finished product in repetitive manufacturing?
- A. Archiving of documents for assembly scrap
- B. Material staging for nex order in sequence
- C. Posting of production costs to the production cost collector
- D. Reduction of associated capacity requirements
- E. Posting of goods receipt for the product
Answer: C,D,E
NEW QUESTION 26
Which chart types does the tabular planning table provide in SAP S/4HANA
- A. Order (dispatched) chart
- B. Capacity requirements chart
- C. Work center capacities chart
- D. Order (pool) chart
Answer: B,C
NEW QUESTION 27
Which business processes are affected by setting in the order type-dependent parameters?
- A. Intiate quality inspections.
- B. Define integration to cost accounting.
- C. Select master data.
- D. Implement engineering changes.
Answer: B,C
NEW QUESTION 28
Which alternative item strategies are available in bills of materials (BOM) in SAP S/4HANA?
- A. By usage probability
- B. Simultaneous
- C. 100% check
- D. First in first out (FIFO)
Answer: A,C
NEW QUESTION 29
What happens to this dependent requirement when you convert the planned order into a production order?
- A. They are converted into a schedule line.
- B. They are converted into a production order.
- C. They are converted into a reservation.
- D. They are converted into a planned order.
Answer: C
NEW QUESTION 30
......